VMware renewal coming up? A 90-day exit plan

How to get from a VMware renewal quote to running on Proxmox VE in about 90 days, and what to do if you can't finish before the renewal date.

If your VMware renewal is less than six months away, you have two decisions running at once: how to migrate, and what to sign before you've finished. Plan them together. A clear migration plan tells you exactly how much VMware you still need on renewal day, and often that turns out to be none.

Can you be off VMware before the renewal date?

Many small and mid-sized environments can move to Proxmox VE in about 90 days when the work starts with an assessment and runs to a fixed plan. Larger estates, or ones built around NSX, vSAN stretched clusters or many appliances, take longer. The assessment in the first two weeks tells you which group you're in, with enough lead time to act on the answer.

The 90-day plan

1

Weeks 1–2

Assess and decide

  • Export the inventory (RVTools) and collect the renewal quote.
  • Classify every VM by migration difficulty.
  • Size the Proxmox platform and confirm which hardware can be reused.
  • Decide: full exit before renewal, or a reduced renewal to cover the tail.
2

Weeks 3–4

Design and order

  • Sign off the target design: cluster, storage, network, backup.
  • Order Proxmox subscriptions and any hardware you need.
  • Write the migration runbook and rollback procedures.
  • Agree the batch schedule and downtime windows with application owners.
3

Weeks 5–8

Build and pilot

  • Build the Proxmox cluster and Proxmox Backup Server.
  • Test HA failover, backup and restore, and performance against VMware.
  • Migrate low-risk VMs first and fix anything the pilot turns up.
  • Free up hosts as they empty and rebuild them into the new cluster.
4

Weeks 9–12

Migrate and decommission

  • Move the remaining workloads in scheduled batches.
  • Validate each batch: connectivity, storage, backups, application checks.
  • Decommission the VMware hosts and vCenter.
  • Hand over as-built documentation and runbooks.

If you can't finish before the renewal date

Don't renew the whole estate by default. Once the plan shows which hosts will still be on VMware at the renewal date, you can:

  • Renew only what's left. Ask for a quote covering just the hosts still running VMware, on the shortest term offered. Broadcom's 72-core minimum order means a very small remainder still pays for 72 cores, so compare that cost with speeding up the last batches.
  • Move the hardest workloads last. Put the simple VMs early so the VMware footprint shrinks quickly, and leave the complex systems for a reduced renewal if needed.
  • Check your contract terms. Notice periods and auto-renewal clauses matter. Our guide on cancelling a VMware ELA or partner contract covers what to look for.

What to do this week

  1. Find your renewal date and notice period, and get the current renewal quote in writing.
  2. Run an RVTools export of your vCenter.
  3. Put your numbers into the Proxmox vs VCF cost calculator for a first estimate.
  4. Book a VMware Exit Assessment to turn the estimate into a plan.

How an engagement runs

All work is delivered remotely. You get a written deliverable at every stage and decide whether to continue after each one.

  1. Free. We confirm what you need and whether we are the right fit.

  2. Inventory, sizing, costs, risks and a plan, in a written report you keep.

  3. 3

    Blueprint

    Target Proxmox design: cluster, storage, network and backup. You sign it off.

  4. 4

    Build & test

    The platform is built and tested (HA, backups, performance) before workloads move.

  5. 5

    Migrate

    Workloads move in planned batches, each with an agreed window and rollback.

  6. 6

    Handover

    As-built documentation, runbooks and knowledge transfer. Ongoing support if you want it.